Could you explain the assumption of 18,000 tonnes of available LACW from Wrexham in 2025?
From this question, we have found an error within Table 5 of the Market Report. The figure of 18ktpa for Wrexham LACW should be zero as the material is contracted to FCC at that time.
However, the corrected Table is as follows and has no effect on the totals used within the Report.
Authority |
Residual MSW ktpa |
Destination |
EFW Capacity ktpa |
Expiry Date |
Available LACW |
|||
2017 |
2025 |
2035 |
|
|
|
2025 |
2035 |
|
Wrexham |
38 |
36 |
36 |
Ferrybridge |
|
2032 |
0 |
36 |
Powys |
21 |
18 |
17 |
Various/Export |
|
2021 |
18 |
17 |
Ceredigion |
18 |
19 |
18 |
Various/Export |
|
2022 |
19 |
18 |
Shropshire |
72 |
70 |
69 |
Battlefields EFW |
96 |
2035 |
0 |
0 |
Telford and Wrekin |
45 |
39 |
39 |
2037 |
0 |
0 |
||
Sandwell |
86 |
85 |
87 |
Four Ashes EFW |
337 |
2037 |
0 |
0 |
Walsall |
71 |
59 |
58 |
2035 |
0 |
0 |
||
Staffordshire |
217 |
174 |
166 |
2035 |
0 |
0 |
||
Stoke |
78 |
76 |
75 |
Hanford EFW |
181 |
2025 |
0 |
75 |
Wolverhampton |
77 |
75 |
75 |
Wolverhampton EFW |
109 |
2023 |
0 |
0 |
Dudley |
91 |
78 |
76 |
Dudley EFW |
93 |
2023 |
0 |
0 |
Birmingham |
382 |
347 |
355 |
Tyseley EFW |
355 |
2024 |
0 |
0 |
North Wales Partnership |
125 |
121 |
117 |
Parc Adfer EFW |
190 |
2035 |
0 |
0 |
Hereford/Worcester |
216 |
179 |
175 |
Hartlebury EFW |
200 |
2030 |
0 |
0 |
Cheshire West/Chester |
67 |
64 |
61 |
Runcorn EFW |
|
2023 |
64 |
61 |
Cheshire East |
86 |
65 |
65 |
Ferrybridge |
|
2022 |
65 |
65 |
Total |
1692 |
1506 |
1490 |
|
1562 |
|
166 |
273 |